Purpose: To bring together, combine and share space for our students and area first responder personnel.
Dekker, Perich & Sabatini - 5% Complete
Roofing has started, and building construction is contingent on a parking agreement. Dekker, Perich & Sabatini (DPS) Roofing construction has started and is about 25% complete.
Plains Builders has been selected as the CMAR contractor.
Construction is estimated to be a 17-month project after the building permit is issued. Awaiting the City of Amarillo to respond back to the architect on a code question about the wall we lost during the high wind a few days ago. As soon as this is answered, the wall will be re-constructed and the roofing will be re-started. The building permit should be received early next week.
Updated 3/22/23